Burke County residents can expect major transportation upgrades in the coming years, as outlined in a summary presentation last week by the Western Piedmont Council of Governments (WPCOG).
The brief presentation was made to Burke County Commissioners during its agenda meeting in preparation for its monthly meeting on Feb. 17. A detailed plan will be presented during that meeting.
The named projects include highway expansions, interchange improvements, new bike lanes, sidewalks, and public transit services. All are designed to improve safety, reduce congestion, and boost economic growth.
Averi Ritchie, transportation planning manager with WPCOG, gave the presentation. The projects are part of the Greater Hickory Metropolitan Planning Organization (GHMPO), which includes Burke County.
Among the projects mentioned were:
Road & Highway Improvements
I-40 Interchange Upgrades
Exit 118 (Old NC 10)
Start: Right of way acquisition in 2025
Construction: 2026
Completion: 2027
Purpose: Improves safety, reduces congestion, and modernizes access.
Exit 103 (Burkemont Road)
Start: Unfunded, awaiting approval
Estimated Completion: To be determined
Purpose: Reduces traffic bottlenecks, improves interchange efficiency.
NC-181 Widening Project (U-5836)
Start: Right of way acquisition in 2027
Construction: 2029
Completion: 2030
Purpose: Expands the road from St. Mary’s Church Road to Morganton city limits, adding bike lanes and sidewalks.
Goat Farm Road Industrial Access (R-5967)
Start: 2023 (ongoing construction)
Completion: 2025
Purpose: Supports Burke Business Park expansion by improving industrial road access.
Bicycle & Pedestrian Improvements
Downtown Morganton Greenway Connector (EB-5807)
Start: 2021 (ongoing)
Completion: 2025
Purpose: Extends walking and biking paths to connect key parts of downtown Morganton.
N.C. 126 Sidewalk Project (BL-0141)
Start: Right of way acquisition in 2026
Construction: 2027
Completion: 2028
Purpose: Improves pedestrian safety and access from Benfield’s Landing to Eastside Burke Avenue in Nebo.
College Street Multi-Use Path (EB-5978)
Start: 2026
Completion: 2027
Purpose: Adds pedestrian and bike-friendly infrastructure from North Green Street to US 70 in Morganton.
Public Transit Expansion
New On-Demand Microtransit Service
Launch Date: Spring 2025
Purpose: Flexible public transit that serves rural areas with same-day ride scheduling.
Asheville-to-Salisbury Passenger Rail Study
Grant Secured: 2024
Study Completion: 2026
Service Launch (if approved): Early 2030s
Purpose: Evaluates the feasibility of passenger train service linking Asheville, Morganton, and Salisbury. A $500,000 federal grant is funding research for the project.





(0) comments
Welcome to the discussion.
Log In
Keep it Clean. Please avoid obscene, vulgar, lewd, racist or sexually-oriented language.
PLEASE TURN OFF YOUR CAPS LOCK.
Don't Threaten. Threats of harming another person will not be tolerated.
Be Truthful. Don't knowingly lie about anyone or anything.
Be Nice. No racism, sexism or any sort of -ism that is degrading to another person.
Be Proactive. Use the 'Report' link on each comment to let us know of abusive posts.
Share with Us. We'd love to hear eyewitness accounts, the history behind an article.